Exploring the factors contributing to public sector building construction delays and mitigation solutions in Pakistan

  • Abdul Aleem

    Department of Architectural Engineering and Design, University of Engineering & Technology Lahore, Lahore 54890, Pakistan

  • Ahmad Riaz orcid

    Department of Architectural Engineering and Design, University of Engineering & Technology Lahore, Lahore 54890, Pakistan

  • Tehseen Ullah

    Department of Architectural Engineering and Design, University of Engineering & Technology Lahore, Lahore 54890, Pakistan

  • Farhan Ali

    Department of Civil Engineering, University of Engineering & Technology Lahore, Lahore 54890, Pakistan

Article ID: 3822
Keywords: construction delays, public sector, mitigation solutions, data analysis, expert stakeholders, Pakistan

Abstract

The construction industry worldwide experiences significant project delays, particularly in the public sector of the construction industry. Construction delays have a substantial effect on the economic development of areas and employment opportunities for the local population, particularly in underdeveloped regions like Balochistan, Pakistan. This research examines the most significant and influential factors causing delays in government building construction within Balochistan, Pakistan. The study presents mitigation solutions and strategies proposed by experts using a Delphi technique for the critical and influential delay factors. The questionnaire survey to collect responses from participants consists of 24 delay factors, which are derived from existing literature and experts’ consultation. A satisfactory degree of data reliability was demonstrated by the survey's 78% response rate. Cronbach's alpha and split-half reliability tests were used in SPSS to assess internal consistency. Delay factors were categorized and ranked based on perceived relevance using the Relative Importance Index (RII). Additionally, to provide an alternate prioritizing of delay variables, the Technique for Order Preference by Similarity to Ideal Solution (TOPSIS) was used with Microsoft Excel and common mathematical formulations. To confirm the stability and robustness of the rankings, a comparison of the RII and TOPSIS results was done. The results establish the groundwork for further studies on building delays and give insightful information for decision-making in the public sector.

Published
2025-12-02
How to Cite
Aleem, A., Riaz, A., Ullah, T., & Ali, F. (2025). Exploring the factors contributing to public sector building construction delays and mitigation solutions in Pakistan. Building Engineering, 3(4). https://doi.org/10.59400/be3822
Section
Article

References

[1]Assafi MN, Hoque MI, Hossain MM, et al. Investigating the causes of construction delay on the perspective of organization-sectors involved in the construction industry of Bangladesh. International Journal of Building Pathology and Adaptation. 2024; 42(4): 788–817.

[2]Tauseef S, Waqas A, Mirza S. Construction. Available online: https://www.pacra.com/view/storage/app/Construction%20-%20PACRA%20Research%20-%20Apr%2724_1712125394.pdf (accessed on 26 January 2025).

[3]Shahzad K, Ahmed E. Impact of China Pakistan Economic Corridor on Economic Development of Balochistan: A Descriptive Study. Journal of Economic Sciences. 2024; 3(1): 57–68.

[4]Arantes A, Ferreira LMDF. Development of delay mitigation measures in construction projects: A combined interpretative structural modeling and MICMAC analysis approach. Production Planning & Control. 2023; 35(10): 1164–1179. doi: 10.1080/09537287.2022.2163934

[5]Amoah K, Okere G, Deshpande A. Construction Delay Analysis: Causes, Impacts, and Mitigation Strategies. Journal of Civil Engineering Research. 2024; 14(1): 1–9.

[6]Rauzana A, Dharma W. Causes of delays in construction projects in the Province of Aceh, Indonesia. PLoS ONE. 2022; 17(1): e0263337.

[7]Gunduz M, Al-Naimi NH. Construction projects delay mitigation using integrated balanced scorecard and quality function deployment. Engineering, Construction and Architectural Management. 2022; 29(5): 2073–2105.

[8]Pérez Y, Ávila J, Sánchez O. Influence of BIM and Lean on mitigating delay factors in building projects. Results in Engineering. 2024; 22: 102236.

[9]Laroza FAR. Investigating construction delays in cold storage projects in the Philippines. International Journal of Construction Management. 2024; 25(3): 1–11.

[10]Haseeb M, Lu X, Bibi A, et al. Causes and effects of delays in large construction projects of Pakistan. Arabian Journal of Business and Management Review. 2011; 1(4): 18–42.

[11]Hassan A, Riaz A. Analysis of skilled labor shortage in the construction industry of developing countries. Building Engineering. 2024; 3(1): 2054.

[12]Irfanullah, Hasmori MF, Memon MH, et al. Critical Factors and Mitigating Measures of Construction Delays of Pakistani Building Construction Projects. International Journal of Sustainable Construction Engineering and Technology. 2023; 14(2): 240–249.

[13]Desai SD, Purohit RR. Investigation on Causes of Delays in Residential Building Construction Project. International Research Journal of Engineering and Technology. 2022; 9(7): 1736–1745.

[14]Yap JBH, Goay PL, Woon YB, et al. Revisiting critical delay factors for construction: Analysing projects in Malaysia. Alexandria Engineering Journal. 2020; 60(1): 1717–1729.

[15]Gunawardena S, Hemachandra D, Kodithuwakkku KASS. Perceived Causes and Effects of Project Delays: A Study of Government Building Construction Projects in the Central Province of Sri Lanka. Proceedings of the 18th International Conference on Business Management. 2022; 18.

[16]Sarwani, Baihaqi I, Utomo C. Causes of Delay in EPC Projects: The Case of Indonesia. International Journal on Advanced Science Engineering and Information Technology. 2024; 14(2):618–628.

[17]Dunama M, Alhaji Ali Z, Usman ML, et al. Causes and Effects of Delays and Disruptions in the Nigerian Construction Industry. International Journal of Innovative Research in Education, Technology & Social Strategies. 2021; 8: 66–75.

[18]Iman G, Jamshid S, Mohamad F, et al. Root Cause Analysis of Construction Oil and Gas Project Delays from Engineering and Construction Management Point of View Using Analytic Hierarchy Process (AHP): A Case Study for National Iranian Oil Company Projects. Industrial Engineering & Management. 2020; 9: 1–15.

[19]Sohu S, Md Kassim TRB, Mustafa A, et al. Assessing the Causes and Effects of Delay and Disruption in Construction Projects in Malaysia. Journal of Applied Engineering Sciences. 2024; 14: 336–341.

[20]Purushothaman MB, San Pedro LNR, GhaffarianHoseini A. Construction projects: interactions of the causes of delays. Smart and Sustainable Built Environment. 2024. doi: 10.1108/SASBE-11-2023-0334

[21]Nadeem M, Jiskani IM, Urwat MS, et al. Analysing delay factors in construction projects using Z-number approach: insights from Pakistan. Canadian Journal of Civil Engineering. 2023; 50(12).

[22]Sohu S, Kassim TRBM, Khan OS. Critical Risk Factors Influencing Time Schedule of Residential Projects in Pakistan. Engineering, Technology and Applied Science Research. 2024; 14: 12636–12639.

[23]Oyediran AO, Akinradewo O, Onososen AO, et al. Key factors contributing to construction delays in high-rise building projects: A case study of Nigeria’s developing urban landscape. Journal of Facilities Management. 2025. doi: 10.1108/jfm-05-2024-0056

[24]Irfanullah, Hasmori MF, Abas NH, et al. Determinants of project time extension factors in the construction of building projects in Pakistan. IOP Conference Series: Earth and Environmental Science. 2024; 1347: 012029.

[25]World Bank Group. Post-Floods Reconstruction and Building Climate Resilience: World Bank Approves $213 Million for the Flood-Affected Communities of Balochistan. World Bank Group; 2023.

[26]Ahmed A. ADB Okays $5 Million for Balochistan’s Flood-Affected Areas. Dawn; 2023.

[27]Ahmad R, Mi H, Fernald LW. Revisiting the potential security threats linked with the China–Pakistan Economic Corridor (CPEC). Journal of the International Council for Small Business. 2020; 1(1): 64–80.

[28]Verma M. Statistical Analysis of Delay Factors in Construction Projects. International Journal for Research in Applied Science and Engineering Technology. 2020; 8(9): 730–738.

[29]Ahmadzai MB, Ye K. A mixed-method investigation of the root causes of construction project delays in Afghanistan. Heliyon. 2025; 11(2): e41923.

[30]Amri TA, Marey-Pérez M. Towards a sustainable construction industry: Delays and cost overrun causes in construction projects of Oman. Journal of Project Management. 2020; 5: 87–102.

[31]Sharma J, Kumari P, Chopra R. Construction and Standardization of Composite Sustainability Scale for GHRM practices with reference to Red Category Industry. Journal of Informatics Education and Research. 2024; 4(1). doi: 10.52783/jier.v4i1.698

[32]Stević Ž, Bouraima MB, Suboti´ M, et al. Assessment of Causes of Delays in the Road Construction Projects in the Benin Republic Using Fuzzy PIPRECIA Method. Mathematical Problems in Engineering. 2022; 1–18.

[33]Ouansrimeang S, Wisaeang KJ. Analyzing the critical delay factors for construction projects in the public sector using relative importance index and machine learning techniques. Journal of Industrial Policy and Development. 2024; 8(8): 6208.

[34]Tchantchane A, Bolaji O, Lutfi MM. Relative Importance Index of Delay Factors in Construction Industry: Case of Dubai. International Journal of Academic Multidisciplinary Research. 2020; 4(3): 1–8.

[35]Alshammari A, Ghazali FEM. A Comprehensive Review of the Factors and Strategies to Mitigate Construction Projects Delays in Saudi Arabia. The Open Construction & Building Technology Journal. 2024; 18: e18748368318470.

[36]Hsieh M, Wang EM, Lee W, et al. Application of HFACS, fuzzy TOPSIS, and AHP for identifying important human error factors in emergency departments in Taiwan. International Journal of Industrial Ergonomics. 2018; 67: 171–179.

[37]Rouzbahani M, Forozandeh M. Identifying and Ranking the Causes of Delay Based on Production Strategies in Manufacturing Projects. Research in Production and Operations Management. 2024; 15(2): 131–151.

[38]HoushmandRad MH, Ghezelbeigloo K. Identifying and ranking the causes of delays in different phases of oil industry projects in EPC contracts using TOPSIS method. In: Proceedings of the Second International Conference on Research Findings in Civil Engineering, Architecture and Urban Planning; June 2022; Tehran, Iran.

[39]Patel KD, Rajgor MB. Mitigation Strategies for Overcoming Delays in High-Rise Construction Projects: A Comprehensive Literature Review. Tuijin Jishu/Journal of Propulsion Technology. 2024; 45: 770–779.

[40]Amanya FS, Njenga G. Construction Delays and Project Cost Overrun: A Case of Regional Cybercrime Center in Gasabo District, Rwanda. Journal of Entrepreneurship & Project Management. 2022; 6(1): 34–52.

[41]Pai SK, Anand N, Mittal AJ. Analysis on Factors Causing Project Delays in Road and Highways Sector in India Using Relative Ranking Index Technique. Journal of Construction Research. 2021; 3(2): 4157.